6) Finishing

Screw

12.  Nail last rows by hand

The last 4 or 5 rows should be installed the same way as first rows due to proximity to wall.









Mirage Classic

  • You may have to trim strips placed along the wall to leave the ½" (13 mm) needed for the expansion gap.

Mirage Engineered

  • You may have to trim strips placed along the wall to leave the ¼" (6 mm) needed for the expansion gap.







Baseboards

13.  Install baseboards

Install transition moldings, stair nosings, and reducers. Reinstall baseboards and quarter rounds. Be sure to nail them to the walls and not the floor so the floor can move naturally. When installing transition molding, pay attention to the color of adjacent strips and make sure they go well together.


14.  Clean floor with Mirage Clean

When installation is completed, vacuum the floor thoroughly, spray light mist of Mirage Clean and clean floor

15.  Install protective felt pads under furniture legs

Place pads under corners of appliances so they do not damage floor as they are moved.

16.  Lift when moving furniture